Implementation of the facility’s MV power supply system using ATS systems, control and monitoring of the power supply status from the BMS level.
GRUNWALDZKI CENTER
Location: Wrocław Area: 40,500 m2
Years of implementation: 2007-2008
Contract value: PLN 5,200,000
SCOPE OF WORK
Complete internal LV electrical installations, MV connections with transformer stations.
CHARACTERISTICS OF THE FACILITY
A complex of 3 office buildings with service premises and an underground garage.
SPECIAL FEATURES