Implementation of the facility’s MV power supply system using ATS systems, control and monitoring of the power supply status from the BMS level.
GRUNWALDZKI CENTER
Location: Wrocław Area: 40,500 m2
Years of implementation: 2007-2008
Contract value: PLN 5,200,000
SCOPE OF WORK
Complete internal LV electrical installations, MV connections with transformer stations.
CHARACTERISTICS OF THE FACILITY
A complex of 3 office buildings with service premises and an underground garage.
SPECIAL FEATURES
Dowiedz się więcej
Sewage Treatment Plant Fonroche Bioquercy – France – 2 MW
Implementation of container development for the Fonroche Bioquercy Sewage Treatment Plant, Eneria, France Genset model: CATERPILLAR CG170-20 Power: 2MWe Feed gas type: Biogas Kontentainer housing
DATA CENTER – OŻARÓW MAZOWIECKI
Power: 1400 kVA Location: Ożarów Mazowiecki Varow Genset model: 2 x CAT® 3512 Eneria prepared the design of the power supply system, carried out tests for the devices, as well as their installation and […]