Implementation of the facility’s MV power supply system using ATS systems, control and monitoring of the power supply status from the BMS level.
GRUNWALDZKI CENTER
Location: Wrocław Area: 40,500 m2
Years of implementation: 2007-2008
Contract value: PLN 5,200,000
SCOPE OF WORK
Complete internal LV electrical installations, MV connections with transformer stations.
CHARACTERISTICS OF THE FACILITY
A complex of 3 office buildings with service premises and an underground garage.
SPECIAL FEATURES
Dowiedz się więcej
Gliwice Industrial Plant – 0.99 MWe
Delivery of a cogeneration system to an industrial plant of 0.999 MWe in a container structure. Model: CG170-12 Powered by: natural gas
ECO CHP Tarnobrzeg – 8 MWe
Investment implementation: Construction of a high-efficiency gas cogeneration source with a capacity of 8 MWe and 7.6 MWt in Tarnobrzeg – GUK II. The implementation includes the development of the project, delivery and […]