Implementation of the facility’s MV power supply system using ATS systems, control and monitoring of the power supply status from the BMS level.
GRUNWALDZKI CENTER
Location: Wrocław Area: 40,500 m2
Years of implementation: 2007-2008
Contract value: PLN 5,200,000
SCOPE OF WORK
Complete internal LV electrical installations, MV connections with transformer stations.
CHARACTERISTICS OF THE FACILITY
A complex of 3 office buildings with service premises and an underground garage.
SPECIAL FEATURES
Dowiedz się więcej
Labat II – France – 0,8 MW
Implementation of container development for Labat, Eneria France Genset model: CATERPILLAR CG132-16 Power: 0.8MWe Feed gas type: Biogas Kontainer housing
Sanplast II
Sanplast II Delivery of a cogeneration system for the Sanplast production plant. Aggregate models: CG132B-16 and CG132B-08 Power: 1.2 MWe Supply gas type: natural gas CAT® high-efficiency cogeneration